LIFT STATION UPGRADE PHASE II
Remaining project items from Phase I of the sanitary sewer phase rehab were bid in October 2017 and awarded to Schmidt Environmental Construction, Inc. The project was paid out of the 2017 Bond and will cost $2,597,625. Our remaining lift stations received valves, bypass connections, new panels and pumps. The project was completed in August 2019.